Published on · Simone Renzi
23 November 2026 · The first physical head frame
Work statusPartially assembled physical prototype. Fit checks in progress; final components and integration remain to be completed.
01 / Construction and prototyping
Time to start building.
It is time to move from theory to practice. We have defined the assemblies in Fusion, and now it is time to start making the parts. I decided to begin with the head because it is the most delicate part of the robot, both in terms of its components and the way they fit together.
In the current design, the head alone will house 23 of the robot’s 53 motors, alongside part of Numero 5’s future brain. Such a compact structure needs room for mechanics, electronics and connections: the frame is the first place to check those clearances in practice.

02 / Construction and prototyping
From OpenSAINT to autonomy.
As always, the starting point is OpenSAINT: an essential foundation for tackling a robot of this complexity. My goal goes beyond remotely controlling that initial foundation. I want to build a Numero 5 that can perceive its surroundings, process information onboard and act autonomously. This is a development goal that will require integration and testing on the physical robot.
That is why it will use components different from those in the original design. I have modified or redesigned almost every component from that foundation, and the head is a concrete example: its internal spaces and mounts must serve the new architecture, as well as reproduce the character’s appearance.
You could say that the head will house the “cerebellum”: the Jetson Orin Nano Super, rated for up to 67 AI TOPS, will handle computer vision and coordination of the ESP32 microcontrollers distributed around the robot. The aim is to recognise people, objects and obstacles along its path. The 67 TOPS figure is a platform specification, not a measurement of robot performance, which must be tested with the actual software.
Speech and decision-making will instead rely on a dedicated Mac Studio running local AI. The design calls for streaming speech recognition and synthesis, STT and TTS, to answer questions and make interaction between person and machine as natural as possible.
03 / Construction and prototyping
A manufacturing process for each part.
I am starting with the head frame, the structure that will support all the other parts. I have divided the components into parts to mill from solid aluminium, parts to 3D-print using FDM, resin parts to produce using MSLA, and sheet-metal parts to laser-cut.
The choice is about more than shape: a part’s purpose, required accuracy, assembly method and the cost of remaking it after a change all matter. At this stage, 3D printing mainly allows me to bring the geometry off the screen and compare the parts physically.

04 / Construction and prototyping
The workshop available to me.
I can do much of the work in my own workshop. For CNC milling I have a Makera Carvera, with a 360 × 240 × 140 mm work area: a useful capacity for metal components too. The size of the parts I can actually machine will also depend on the tool and how the stock is held.
The QIDI X-Max 3 has a 325 × 325 × 315 mm build volume, allowing fairly generous prototype dimensions. For resin, the Saturn 16K offers approximately 211 × 118 × 220 mm; it uses MSLA, with exposure through an LCD screen.
For very thin sheet metal I have an xTool F1 Ultra. Aluminium requires staying within the machine’s limits: the manufacturer specifies cutting 0.2 mm sheet. For greater thicknesses I will use a friend’s workshop, agreeing on a process suited to the material and the planned parts, up to 5 mm where compatible with the equipment.

05 / Construction and prototyping
3D printing first, aluminium later.
I do not expect the CAD for every component to be final yet. Experience has taught me that assembly always reveals details to revisit: a fit that needs correcting, an awkwardly positioned fastener, or a small change that seemed unnecessary on screen.
My plan is therefore to assemble the robot with 3D-printed parts first, checking the fit before milling aluminium blocks. Printing serves as a dimensional and assembly check; it does not replace later testing of the strength and behaviour of the final components.
06 / Construction and prototyping
Always keep an eye on costs.
There are two reasons for this approach. The first is cost: at the prices I am considering for this project, a 1 kg spool of ASA costs around €18 and lets me print almost the entire head. The central frame block alone, by contrast, requires a 4 cm-thick aluminium plate costing around €57, before machining even begins.
The second is time. In this workflow, making parts from solid stock involves more preparation, workholding and machining than producing an initial test print. If a dimension needs changing, I would rather discover it on a printed prototype than on a machined part whose material and fabrication could cost hundreds of euros.
These are indicative purchasing costs for my project, not a complete quotation: fasteners, possible reprints, tools and working time still have to be considered. But they explain the approach: spend a little to learn early, before committing to final materials and fabrication.
07 / Construction and prototyping
The first assembly already tells a story.
In the workbench photograph, the frame is still only partially assembled. Its stacked planes, openings and interfaces will have to work with the rest of the head. The motors and electronics are not yet all installed: this is precisely the right time to examine the structure before the other components make assembly more complicated.
Next I want to check how the mating surfaces sit, whether the holes align and whether tools can reach the fixing points. I also want to establish the order in which to assemble and dismantle the parts. A robot will need to be opened for maintenance: it is not enough for a component to fit once; it must remain accessible when everything else is in place.
Layer lines and temporary finishes belong to this stage. I am looking for answers about fit, rather than the final appearance. If a correction is needed, I will return to Fusion, update the component and repeat the check: this is where a physical prototype starts providing information the digital model alone cannot give.
08 / Construction and prototyping
The next step.
Before moving to aluminium I want to complete the head’s trial assembly, compare the physical clearances with the assembly model and record the necessary revisions. Mounts, motors, the Jetson and cable routing will follow, one subassembly at a time.
After so many hours in CAD, having the first parts on the workbench changes how the project feels. Numero 5 is beginning to occupy real space. For now it is a partial frame, but it is the first tangible step in a build I want to pursue methodically, keeping both time and costs in view.
Documentation and references
I took these photographs in my workshop to document the stage described in this article. Manufacturer references concern platform and machine specifications.